Title: A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations
Authors: Lamas Vilches, Patricio
Demeulemeester, Erik
Issue Date: Jun-2014
Publisher: KU Leuven - Faculty of Economics and Business
Series Title: FEB Research Report KBI_1412
Abstract: The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts
with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure
outperforms two other published methods, assuming different robustness measures.
Publication status: published
KU Leuven publication type: IR
Appears in Collections:Research Center for Operations Management, Leuven

Files in This Item:
File Description Status SizeFormat
KBI_1412.pdfA purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations Published 719KbAdobe PDFView/Open

 


All items in Lirias are protected by copyright, with all rights reserved.