DTEW - KBI_0605

Publication date: 2006-01-01
26
Publisher: K.U.Leuven - Faculty of Economics and Applied Economics

Author:

Van de Vonder, S
Ballestin, F ; Demeulemeester, Erik ; Herroelen, Willy

Keywords:

Project scheduling, Scheduling, Reactive scheduling, Research, Uncertainty, Stability

Abstract:

This paper describes new heuristic reactive project scheduling procedures that may be used to repair resource-constrained roject baseline schedules that suer from multiple activity duration disruptions during project execution.The objective is to minimize the deviations between the baseline schedule and the schedule that is actually realized.We discuss computational results obtained with priority-rule based schedule generation schemes, a sampling approach and a weighted-earliness tardiness heuristic on a set of randomly generated project instances.