Title: A method for the construction of stable baseline schedules by anticipation of disruptions
Authors: Herroelen, Willy
Leus, Roel #
Issue Date: 2002
Conference: INFORMS Annual Meeting location:San Jose (U.S.A.), Nov. 17-20 date:2002
Abstract: We present models to develop project baseline schedules that can absorb a small predetermined number of disruptions in activity durations without affecting the planning of other activities, such that co-ordination of resources and material procurement can be performed as smoothly as possible. We report on computational experience on a benchmark dataset.