Title: An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem
Authors: Vanhoucke, Mario ×
Demeulemeester, Erik
Herroelen, Willy #
Issue Date: 2001
Publisher: Kluwer academic publ
Series Title: Annals of operations research vol:102 pages:179-196
Abstract: In this paper we study the resource-constrained project scheduling problem with weighted earliness-tardinesss penalty costs. Project activities are assumed to have a known deterministic due date, a unit earliness as well as a unit tardiness penalty cost and constant renewable resource requirements. The objective is to schedule the activities in order to minimize the total weighted earliness-tardinesss penalty cost of the project subject to the finish-start precedence constraints and the constant renewable resource availability constraints. With these features the problem becomes highly attractive in just-in-time environments.
ISSN: 0254-5330
Publication status: published
KU Leuven publication type: IT
Appears in Collections:Research Center for Operations Management, Leuven
× corresponding author
# (joint) last author

Files in This Item:
File Status SizeFormat
exact procedure.pdf Published 277KbAdobe PDFView/Open


All items in Lirias are protected by copyright, with all rights reserved.

© Web of science