Title: Robust resource allocation decisions in resource-constrained projects
Authors: Deblaere, Filip ×
Demeulemeester, Erik
Herroelen, Willy
Van de Vonder, Stijn #
Issue Date: Feb-2007
Publisher: Blackwell publishing
Series Title: Decision sciences vol:38 issue:1 pages:5-37
Abstract: The well-known deterministic resource-constrained project scheduling problem involves the determination of a predictive schedule (baseline schedule or pre-schedule) of the project activities that satisfies the finish-start precedence relations and the renewable resource constraints under the objective of minimizing the project duration. This baseline schedule serves as a baseline for the execution of the project. During execution, however, the project can be subject to several types of disruptions that may disturb the baseline schedule. Management must then rely on a reactive scheduling procedure for revising or reoptimizing the baseline schedule. The objective of our research is to develop procedures for allocating resources to the activities of a given baseline schedule in order to maximize its stability in the presence of activity duration variability. We propose three integer programming-based heuristics and one constructive procedure for resource allocation. We derive lower bounds for schedule stability and report on computational results obtained on a set of benchmark problems.
ISSN: 0011-7315
Publication status: published
KU Leuven publication type: IT
Appears in Collections:Research Center for Operations Management, Leuven
× corresponding author
# (joint) last author

Files in This Item:
File Status SizeFormat
Robustresource.pdf Published 471KbAdobe PDFView/Open Request a copy

These files are only available to some KU Leuven Association staff members


All items in Lirias are protected by copyright, with all rights reserved.

© Web of science